Skip to content
AirPermitHub

40 CFR Part 60, Subpart Ja

NSPS Subpart Ja: Petroleum Refineries for Which Construction, Reconstruction, or Modification Commenced After May 14, 2007

Subpart Ja—Standards of Performance for Petroleum Refineries for Which Construction, Reconstruction, or Modification Commenced After May 14, 2007
Rule text from eCFRLast amended in eCFR 2018-11-26

Where this text comes from

Citation
40 CFR Part 60, Subpart Ja
Official title
Subpart Ja—Standards of Performance for Petroleum Refineries for Which Construction, Reconstruction, or Modification Commenced After May 14, 2007
Text as of
eCFR current through 2026-10-28, retrieved 2026-10-30
Latest amendment
2018-11-26
Source note
73 FR 35867, June 24, 2008, unless otherwise noted.

Headings and quoted sections on this page are copied from the eCFR text of Subpart Ja without changes. AirPermitHub checks eCFR every week and reviews any change before publishing it, so this page can trail eCFR by a few days. eCFR is maintained by the Office of the Federal Register and the Government Publishing Office. It is not an official legal edition of the CFR, and it does not show how an agency has applied the rule in a permit.

Where to look in Subpart Ja

Sections sorted by the words in their eCFR headings. Read the full section before relying on it; requirements often sit in more than one place.

Who is covered
§ 60.100a
Standards and limits
§ 60.103a
Tests, methods, and calculations
§ 60.104a
Notifications, reports, records
§ 60.108a
Definitions
§ 60.101a
Modification and reconstruction
§ 60.100a
Who implements it
§ 60.109a

Who the subpart covers, in the rule's own words

The sections that set out what the subpart applies to, quoted in full from eCFR. Dates, sizes, and other figures are the rule's, not AirPermitHub's.

§ 60.100a Applicability, designation of affected facility, and reconstruction.

Open in eCFR

(a) The provisions of this subpart apply to the following affected facilities in petroleum refineries: fluid catalytic cracking units (FCCU), fluid coking units (FCU), delayed coking units, fuel gas combustion devices (including process heaters), flares and sulfur recovery plants. The sulfur recovery plant need not be physically located within the boundaries of a petroleum refinery to be an affected facility, provided it processes gases produced within a petroleum refinery.

(b) Except for flares and delayed coking units, the provisions of this subpart apply only to affected facilities under paragraph (a) of this section which either commence construction, modification or reconstruction after May 14, 2007, or elect to comply with the provisions of this subpart in lieu of complying with the provisions in subpart J of this part. For flares, the provisions of this subpart apply only to flares which commence construction, modification or reconstruction after June 24, 2008. For the purposes of this subpart, a modification to a flare commences when a project that includes any of the activities in paragraphs (c)(1) or (2) of this section is commenced. For delayed coking units, the provisions of this subpart apply to delayed coking units that commence construction, reconstruction or modification on the earliest of the following dates:

(1) May 14, 2007, for such activities that involve a “delayed coking unit” defined as follows: one or more refinery process units in which high molecular weight petroleum derivatives are thermally cracked and petroleum coke is produced in a series of closed, batch system reactors;

(2) December 22, 2008, for such activities that involve a “delayed coking unit” defined as follows: a refinery process unit in which high molecular weight petroleum derivatives are thermally cracked and petroleum coke is produced in a series of closed, batch system reactors. A delayed coking unit consists of the coke drums and associated fractionator;

(3) September 12, 2012, for such activities that involve a “delayed coking unit” as defined in § 60.101a.

(c) For all affected facilities other than flares, the provisions in § 60.14 regarding modification apply. As provided in § 60.14(f), the special provisions set forth under this subpart shall supersede the provisions in § 60.14 with respect to flares. For the purposes of this subpart, a modification to a flare occurs as provided in paragraphs (c)(1) or (2) of this section.

(1) Any new piping from a refinery process unit, including ancillary equipment, or a fuel gas system is physically connected to the flare (e.g., for direct emergency relief or some form of continuous or intermittent venting). However, the connections described in paragraphs (c)(1)(i) through (vii) of this section are not considered modifications of a flare.

(i) Connections made to install monitoring systems to the flare.

Show the rest of § 60.100a (8 more paragraphs)

(ii) Connections made to install a flare gas recovery system or connections made to upgrade or enhance components of a flare gas recovery system (e.g., addition of compressors or recycle lines).

(iii) Connections made to replace or upgrade existing pressure relief or safety valves, provided the new pressure relief or safety valve has a set point opening pressure no lower and an internal diameter no greater than the existing equipment being replaced or upgraded.

(iv) Connections made for flare gas sulfur removal.

(v) Connections made to install back-up (redundant) equipment associated with the flare (such as a back-up compressor) that does not increase the capacity of the flare.

(vi) Replacing piping or moving an existing connection from a refinery process unit to a new location in the same flare, provided the new pipe diameter is less than or equal to the diameter of the pipe/connection being replaced/moved.

(vii) Connections that interconnect two or more flares.

(2) A flare is physically altered to increase the flow capacity of the flare.

(d) For purposes of this subpart, under § 60.15, the “fixed capital cost of the new components” includes the fixed capital cost of all depreciable components which are or will be replaced pursuant to all continuous programs of component replacement which are commenced within any 2-year period following the relevant applicability date specified in paragraph (b) of this section.

[73 FR 35867, June 24, 2008, as amended at 77 FR 56464, Sep. 12, 2012; 80 FR 75230, Dec. 1, 2015]

Every section in Subpart Ja

10 sections and 1 tables, in eCFR order. Each link opens the official text.

  • § 60.100aApplicability, designation of affected facility, and reconstruction.Amended 2016-10-31
  • § 60.101aDefinitions.Amended 2016-10-31
  • § 60.102aEmissions limitations.Amended 2016-10-31
  • § 60.103aDesign, equipment, work practice or operational standards.Amended 2016-10-31
  • § 60.104aPerformance tests.Amended 2016-10-31
  • § 60.105aMonitoring of emissions and operations for fluid catalytic cracking units (FCCU) and fluid coking units (FCU).Amended 2018-11-26
  • § 60.106aMonitoring of emissions and operations for sulfur recovery plants.Amended 2018-11-26
  • § 60.107aMonitoring of emissions and operations for fuel gas combustion devices and flares.Amended 2016-10-31
  • § 60.108aRecordkeeping and reporting requirements.Amended 2016-10-31
  • § 60.109aDelegation of authority.Amended 2016-10-31

Amendment history

Dates on which eCFR records a change to any section of Subpart Ja, newest first.

  • 2018-11-26
  • 2018-11-14
  • 2016-10-31

To read the rulemakings behind these dates, search the Federal Register for Subpart Ja. New EPA air rules and proposals also appear in the Federal Air Rule Tracker.

AirPermitHub provides educational, engineering, research, and compliance-support information. Information provided by the platform does not constitute legal advice and should not replace review of applicable regulations, permits, agency guidance, or consultation with qualified professionals. Full disclaimer