NESHAP Subpart BBBBBB (6B): Source Category: Gasoline Distribution Bulk Terminals, Bulk Plants, and Pipeline Facilities

Subpart BBBBBB—National Emission Standards for Hazardous Air Pollutants for Source Category: Gasoline Distribution Bulk Terminals, Bulk Plants, and Pipeline Facilities
Rule text from eCFRLast amended in eCFR 2024-07-08

Where this text comes from

Citation
40 CFR Part 63, Subpart BBBBBB
Official title
Subpart BBBBBB—National Emission Standards for Hazardous Air Pollutants for Source Category: Gasoline Distribution Bulk Terminals, Bulk Plants, and Pipeline Facilities
Text as of
eCFR current through 2026-10-28, retrieved 2026-10-30
Latest amendment
2024-07-08
Source note
73 FR 1933, Jan. 10, 2008, unless otherwise noted.

Headings and quoted sections on this page are copied from the eCFR text of Subpart BBBBBB without changes. AirPermitHub checks eCFR every week and reviews any change before publishing it, so this page can trail eCFR by a few days. eCFR is maintained by the Office of the Federal Register and the Government Publishing Office. It is not an official legal edition of the CFR, and it does not show how an agency has applied the rule in a permit.

Where to look in Subpart BBBBBB

Sections sorted by the words in their eCFR headings. Read the full section before relying on it; requirements often sit in more than one place.

Compliance dates
§ 63.11083
Showing compliance
§ 63.11083
Monitoring
§ 63.11092
Tests, methods, and calculations
§ 63.11092
Notifications, reports, records
§ 63.11093§ 63.11094§ 63.11095
Definitions
§ 63.11100
Who implements it
§ 63.11099
General provisions
§ 63.11098

Who the subpart covers, in the rule's own words

The sections that set out what the subpart applies to, quoted in full from eCFR. Dates, sizes, and other figures are the rule's, not AirPermitHub's.

§ 63.11080 What is the purpose of this subpart?

Open in eCFR

This subpart establishes national emission limitations and management practices for hazardous air pollutants (HAP) emitted from area source gasoline distribution bulk terminals, bulk plants, and pipeline facilities. This subpart also establishes requirements to demonstrate compliance with the emission limitations and management practices.

§ 63.11081 Am I subject to the requirements in this subpart?

Open in eCFR

(a) The affected source to which this subpart applies is each area source bulk gasoline terminal, pipeline breakout station, pipeline pumping station, and bulk gasoline plant identified in paragraphs (a)(1) through (4) of this section. You are subject to the requirements in this subpart if you own or operate one or more of the affected area sources identified in paragraphs (a)(1) through (4) of this section.

(1) A bulk gasoline terminal that is not subject to the control requirements of 40 CFR part 63, subpart R (§§ 63.422, 63.423, and 63.424) or 40 CFR part 63, subpart CC (§§ 63.646, 63.648, 63.649, and 63.650).

(2) A pipeline breakout station that is not subject to the control requirements of 40 CFR part 63, subpart R (§§ 63.423 and 63.424).

(3) A pipeline pumping station.

(4) A bulk gasoline plant.

(b) If you are an owner or operator of affected sources, as defined in (a)(1) through (4) of this section, you are not required to meet the obligation to obtain a permit under 40 CFR part 70 or 40 CFR part 71 as a result of being subject to this subpart. However, you are still subject to the requirement to apply for and obtain a permit under 40 CFR part 70 or 40 CFR part 71 if you meet one or more of the applicability criteria found in 40 CFR 70.3(a) and (b) or 40 CFR part 71.3(a) and (b).

(c) Gasoline storage tanks that are located at affected sources identified in paragraphs (a)(1) through (4) of this section, and that are used only for dispensing gasoline in a manner consistent with tanks located at a gasoline dispensing facility as defined in § 63.11132, are not subject to any of the requirements in this subpart. These tanks must comply with subpart CCCCCC of this part.

(d) The loading of aviation gasoline into storage tanks at airports, and the subsequent transfer of aviation gasoline within the airport, is not subject to this subpart.

Show the rest of § 63.11081 (6 more paragraphs)

(e) The loading of gasoline into marine tank vessels at bulk facilities is not subject to this subpart.

(f) If your affected source's throughput ever exceeds an applicable throughput threshold in the definition of “bulk gasoline terminal” or in item 1 in table 2 to this subpart, the affected source will remain subject to the requirements for sources above the threshold, even if the affected source throughput later falls below the applicable throughput threshold. If your bulk gasoline plant's annual average gasoline throughput ever reaches or exceeds 4,000 gallons per day, the bulk gasoline plant will remain subject to the vapor balancing requirements, even if the affected source annual average gasoline throughput later falls below 4,000 gallons per day.

(g) For the purpose of determining gasoline throughput, as used in the definition of bulk gasoline plant and bulk gasoline terminal, the 20,000 gallons per day threshold throughput is the maximum calculated design throughout for any day, and is not an average. An enforceable State, local, or Tribal permit limitation on throughput, established prior to the applicable compliance date, may be used in lieu of the 20,000 gallons per day design capacity throughput threshold to determine whether the facility is a bulk gasoline plant or a bulk gasoline terminal.

(h) Storage tanks that are used to load gasoline into a cargo tank for the on-site redistribution of gasoline to another storage tank are subject to this subpart.

(i) For any affected source subject to the provisions of this subpart and another Federal rule, you may elect to comply only with the more stringent provisions of the applicable subparts. You must consider all provisions of the rules, including monitoring, recordkeeping, and reporting. You must identify the affected source and provisions with which you will comply in your Notification of Compliance Status required under § 63.11093. You also must demonstrate in your Notification of Compliance Status that each provision with which you will comply is at least as stringent as the otherwise applicable requirements in this subpart. You are responsible for making accurate determinations concerning the more stringent provisions; noncompliance with this rule is not excused if it is later determined that your determination was in error, and, as a result, you are violating this subpart. Compliance with this rule is your responsibility, and the Notification of Compliance Status does not alter or affect that responsibility.

(j) For new or reconstructed affected sources, as specified in § 63.11082(b) and (c), recordkeeping to document applicable throughput must begin upon startup of the affected source. For existing sources, as specified in § 63.11082(d), recordkeeping to document applicable throughput must begin on January 10, 2008. Records required under this paragraph shall be kept for a period of 5 years.

[73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4176, Jan. 24, 2011; 89 FR 39373, May 8, 2024]

Every section in Subpart BBBBBB

16 sections and 4 tables, in eCFR order. Each link opens the official text.

What This Subpart Covers

  • § 63.11080What is the purpose of this subpart?Amended 2016-12-22
  • § 63.11081Am I subject to the requirements in this subpart?Amended 2024-07-08
  • § 63.11082What parts of my affected source does this subpart cover?Amended 2024-07-08
  • § 63.11083When do I have to comply with this subpart?Amended 2024-07-08

Emission Limitations and Management Practices

  • § 63.11085What are my general duties to minimize emissions?Amended 2024-07-08
  • § 63.11086What requirements must I meet if my facility is a bulk gasoline plant?Amended 2024-07-08
  • § 63.11087What requirements must I meet for gasoline storage tanks if my facility is a bulk gasoline terminal, pipeline breakout station, or pipeline pumping station?Amended 2024-07-08
  • § 63.11088What requirements must I meet for gasoline loading racks if my facility is a bulk gasoline terminal?Amended 2024-07-08
  • § 63.11089What requirements must I meet for equipment leak inspections if my facility is a bulk gasoline terminal, bulk gasoline plant, pipeline breakout station, or pipeline pumping station?Amended 2024-07-08

Testing and Monitoring Requirements

  • § 63.11092What testing and monitoring requirements must I meet?Amended 2024-07-08

Notifications, Records, and Reports

  • § 63.11093What notifications must I submit and when?Amended 2024-07-08
  • § 63.11094What are my recordkeeping requirements?Amended 2024-07-08
  • § 63.11095What are my reporting requirements?Amended 2024-07-08

Other Requirements and Information

  • § 63.11098What parts of the General Provisions apply to me?Amended 2024-07-08
  • § 63.11099Who implements and enforces this subpart?Amended 2024-07-08
  • § 63.11100What definitions apply to this subpart?Amended 2024-07-08

Amendment history

Dates on which eCFR records a change to any section of Subpart BBBBBB, newest first.

  • 2024-07-08
  • 2024-07-05
  • 2024-05-08
  • 2021-01-18
  • 2020-11-19
  • 2016-12-22

To read the rulemakings behind these dates, search the Federal Register for Subpart BBBBBB. New EPA air rules and proposals also appear in the Federal Air Rule Tracker.

AirPermitHub provides educational, engineering, research, and compliance-support information. Information provided by the platform does not constitute legal advice and should not replace review of applicable regulations, permits, agency guidance, or consultation with qualified professionals. Full disclaimer