Where this text comes from
- Citation
- 40 CFR Part 63, Subpart DDDDD
- Official title
- Subpart DDDDD—National Emission Standards for Hazardous Air Pollutants for Major Sources: Industrial, Commercial, and Institutional Boilers and Process Heaters
- Text as of
- eCFR current through 2026-10-28, retrieved 2026-10-30
- Latest amendment
- 2022-12-05
- Source note
- 76 FR 15664, Mar. 21, 2011, unless otherwise noted.
Headings and quoted sections on this page are copied from the eCFR text of Subpart DDDDD without changes. AirPermitHub checks eCFR every week and reviews any change before publishing it, so this page can trail eCFR by a few days. eCFR is maintained by the Office of the Federal Register and the Government Publishing Office. It is not an official legal edition of the CFR, and it does not show how an agency has applied the rule in a permit.
Where to look in Subpart DDDDD
Sections sorted by the words in their eCFR headings. Read the full section before relying on it; requirements often sit in more than one place.
Who the subpart covers, in the rule's own words
The sections that set out what the subpart applies to, quoted in full from eCFR. Dates, sizes, and other figures are the rule's, not AirPermitHub's.
§ 63.7480 What is the purpose of this subpart?
Open in eCFRThis subpart establishes national emission limitations and work practice standards for hazardous air pollutants (HAP) emitted from industrial, commercial, and institutional boilers and process heaters located at major sources of HAP. This subpart also establishes requirements to demonstrate initial and continuous compliance with the emission limitations and work practice standards.
§ 63.7485 Am I subject to this subpart?
Open in eCFRYou are subject to this subpart if you own or operate an industrial, commercial, or institutional boiler or process heater as defined in § 63.7575 that is located at, or is part of, a major source of HAP, except as specified in § 63.7491. For purposes of this subpart, a major source of HAP is as defined in § 63.2, except that for oil and natural gas production facilities, a major source of HAP is as defined in § 63.7575.
[78 FR 7162, Jan. 31, 2013]
§ 63.7490 What is the affected source of this subpart?
Open in eCFR(a) This subpart applies to new, reconstructed, and existing affected sources as described in paragraphs (a)(1) and (2) of this section.
(1) The affected source of this subpart is the collection at a major source of all existing industrial, commercial, and institutional boilers and process heaters within a subcategory as defined in § 63.7575.
(2) The affected source of this subpart is each new or reconstructed industrial, commercial, or institutional boiler or process heater, as defined in § 63.7575, located at a major source.
(b) A boiler or process heater is new if you commence construction of the boiler or process heater after June 4, 2010, and you meet the applicability criteria at the time you commence construction.
(c) A boiler or process heater is reconstructed if you meet the reconstruction criteria as defined in § 63.2, you commence reconstruction after June 4, 2010, and you meet the applicability criteria at the time you commence reconstruction.
(d) A boiler or process heater is existing if it is not new or reconstructed.
(e) An existing electric utility steam generating unit (EGU) that meets the applicability requirements of this subpart after the effective date of this final rule due to a change (e.g., fuel switch) is considered to be an existing source under this subpart.
[76 FR 15664, Mar. 21, 2011, as amended at 78 FR 7162, Jan. 31, 2013]
Every section in Subpart DDDDD
26 sections and 15 tables, in eCFR order. Each link opens the official text.
What This Subpart Covers
- § 63.7480What is the purpose of this subpart?Amended 2016-08-24
- § 63.7485Am I subject to this subpart?Amended 2016-08-24
- § 63.7490What is the affected source of this subpart?Amended 2016-08-24
- § 63.7491Are any boilers or process heaters not subject to this subpart?Amended 2016-08-24
- § 63.7495When do I have to comply with this subpart?Amended 2016-08-24
Emission Limitations and Work Practice Standards
General Compliance Requirements
- § 63.7505What are my general requirements for complying with this subpart?Amended 2022-12-05
Testing, Fuel Analyses, and Initial Compliance Requirements
- § 63.7510What are my initial compliance requirements and by what date must I conduct them?Amended 2022-12-05
- § 63.7515When must I conduct subsequent performance tests, fuel analyses, or tune-ups?Amended 2022-12-05
- § 63.7520What stack tests and procedures must I use?Amended 2022-12-05
- § 63.7521What fuel analyses, fuel specification, and procedures must I use?Amended 2022-12-05
- § 63.7522Can I use emissions averaging to comply with this subpart?Amended 2022-12-05
- § 63.7525What are my monitoring, installation, operation, and maintenance requirements?Amended 2022-12-05
- § 63.7530How do I demonstrate initial compliance with the emission limitations, fuel specifications and work practice standards?Amended 2022-12-05
- § 63.7533Can I use efficiency credits earned from implementation of energy conservation measures to comply with this subpart?Amended 2022-12-05
Continuous Compliance Requirements
- § 63.7535Is there a minimum amount of monitoring data I must obtain?Amended 2016-08-24
- § 63.7540How do I demonstrate continuous compliance with the emission limitations, fuel specifications and work practice standards?Amended 2022-12-05
- § 63.7541How do I demonstrate continuous compliance under the emissions averaging provision?Amended 2016-08-24
Notification, Reports, and Records
Other Requirements and Information
Tables and appendices
- TableTable 1 to Subpart DDDDD of Part 63—Emission Limits for New or Reconstructed Boilers and Process Heaters cSee eCFR
- TableTable 2 to Subpart DDDDD of Part 63—Emission Limits for Existing Boilers and Process Heaters dSee eCFR
- TableTable 3 to Subpart DDDDD of Part 63—Work Practice StandardsSee eCFR
- TableTable 4 to Subpart DDDDD of Part 63—Operating Limits for Boilers and Process HeatersSee eCFR
- TableTable 5 to Subpart DDDDD of Part 63—Performance Testing RequirementsSee eCFR
- TableTable 6 to Subpart DDDDD of Part 63—Fuel Analysis RequirementsSee eCFR
- TableTable 7 to Subpart DDDDD of Part 63—Establishing Operating Limits a bSee eCFR
- TableTable 8 to Subpart DDDDD of Part 63—Demonstrating Continuous ComplianceSee eCFR
- TableTable 9 to Subpart DDDDD of Part 63—Reporting RequirementsSee eCFR
- TableTable 10 to Subpart DDDDD of Part 63—Applicability of General Provisions to Subpart DDDDDSee eCFR
- TableTable 11 to Subpart DDDDD of Part 63—Alternative Emission Limits for New or Reconstructed Boilers and Process Heaters That Commenced Construction or Reconstruction After June 4, 2010, and Before May 20, 2011See eCFR
- TableTable 12 to Subpart DDDDD of Part 63—Alternative Emission Limits for New or Reconstructed Boilers and Process Heaters That Commenced Construction or Reconstruction After May 20, 2011, and Before December 23, 2011See eCFR
- TableTable 13 to Subpart DDDDD of Part 63—Alternative Emission Limits for New or Reconstructed Boilers and Process Heaters That Commenced Construction or Reconstruction After December 23, 2011, and Before April 1, 2013See eCFR
- TableTable 14 to Subpart DDDDD of Part 63—Alternative Emission Limits for New or Reconstructed Boilers and Process Heaters cSee eCFR
- TableTable 15 to Subpart DDDDD of Part 63—Alternative Emission Limits for Existing Boilers and Process Heaters dSee eCFR
Amendment history
Dates on which eCFR records a change to any section of Subpart DDDDD, newest first.
- 2022-12-05
- 2022-10-06
- 2021-01-20
- 2020-12-28
- 2020-11-19
- 2019-01-14
- 2018-11-14
- 2016-08-24
To read the rulemakings behind these dates, search the Federal Register for Subpart DDDDD. New EPA air rules and proposals also appear in the Federal Air Rule Tracker.
AirPermitHub provides educational, engineering, research, and compliance-support information. Information provided by the platform does not constitute legal advice and should not replace review of applicable regulations, permits, agency guidance, or consultation with qualified professionals. Full disclaimer